Projects which will be implemented in 2015-2020
For the development of enterprises is needed investment in the amount of 88.2 million dollars.
Reconstruction and modernization of production of urea and ammonium nitrate
- Justification: The Presidential Decree PP№1623 from 04.10.2011
- The project cost for PFS – 21.26 million dollars.
- Investment obligations – 11.2 million dollars.
- Project implementation period - 2015-2017.
Upgrading of equipment which is physically and morally outdated
- Justification: The Protocol №11 from 08.02.2016 of the Presidium of the Cabinet of Ministers.
- Investment obligations - 67.0 million dollars.
- Project implementation period - 2016-2020.
The organization of manufacture of new products
- Justification: The need for diversification of production.
- The project cost - 10.0 million dollars.
- Investment obligations - 10.0 million dollars.
- Project implementation period - 2015-2020.
Forecasts of the enterprise for the coming 5 years related to the implementation of the project "Reconstruction and modernization of production of urea and ammonium nitrate” in accordance with the Decree of the President of the Republic of Uzbekistan # PD-1623 from October 4, 2011" On the Program of priority measures to increase production volumes and the development of new types of competitive products ", as well as in accordance with the Decree of the President of the Republic of Uzbekistan # PD-2458 from December 25, 2015" On investment program of Uzbekistan for 2016”.